Brazil. Infrastructure Investment Opportunities Tokyo,
|
|
- Kátia Pereira Salazar
- 8 Há anos
- Visualizações:
Transcrição
1 Brazil Infrastructure Investment Opportunities Tokyo, Guilherme Walder Mora Ramalho Infrastructure Advisor Executive Office of the President of Brazil
2 PAC Growth Acceleration Program In 2007 PAC 1 To accelerate the pace of economic growth To increase employment and income rates To decrease social and regional inequalities To overcome infrastructure bottlenecks In 2009, a new goal To reduce the impact of the international economic crisis countercyclical policy In 2011, a new stage: PAC
3 GROWTH ACCELERATION PROGRAM PAC 1, Infrastructure projects in three areas US$ billion Area After 2010 TOTAL LOGISTICS POWER G&T SOCIAL AND URBAN TOTAL
4 GROWTH ACCELERATION PROGRAM PAC 2, Preliminary investment forecast US$ billion Area After 2014 TOTAL LOGISTICS POWER G&T SOCIAL AND URBAN TOTAL
5 INVESTMENT OPPORTUNITIES: POWER GENERATION AND TRANSMISSION HIGHWAYS RAILROADS AIRPORTS PORTS URBAN MOBILITY HOUSING AND SANITATION
6 ELECTRIC POWER GENERATION AND TRANSMISSION
7 ELECTRIC POWER SYSTEM GENERAL FEATURES Installed Capacity 105,066 MW Number of Customers 64.6 million Energy Production TWh / year 60% of South America Peak 67,632 MW Transmission Lines 96,207 km 230kV Source: Ministry of Mines and Energy
8 ELECTRIC POWER GENERATION Priority to competitive, renewable sources with low carbon emission Annual tenders to contract energy in the regulated contracts environment Hydroelectric power plants energy to be delivered at the fifth year after the tender Thermal power plants and others energy to be delivered at the third year after the tender Tenders planned HPP 47,870 MW US$ 57.9 billion
9 ALTERNATIVE ENERGY SOURCES From 2011 to Wind Power Plants MW 3 Biomass TPP 224 MW TOTAL PROJECTED INVESTMENT- US$ 5.5 billion
10 TRANSMISSION LINES Large Interconnections km Regional Lines km TOTAL PROJECTED INVESTMENT- US$ 14 billion
11 Alternative Energy Sources Wind Power Aratua 1 Areia Branca Miassaba 3 Coqueiros Quixaba Garças Lagoa Seca Vento do Oeste Dunas do Paracuru Taíba Águia Taíba Andorinha Icarai I e II Araras Buriti Cajucoco Morro dos ventos I, III, IV, VI, IX Rei dos Ventos 1, 3 Eurus VI Colonia Embuaca Cabeco Preto Mangue Seco 1, 2, 3 e 5 Sangradouro 3 Sangradouro 2 Osório 2 Fazenda Rosário 3 PAC 2 Barra dos Coqueiros Mar e Terra Santa Clara I Guirapa Guanambi Igapora Candiba Serra do salto Alvorada Ilheus Pindai Pedra do Reino Seabra Macaubas Pajeu do vento Coxilha Negra V Coxilha Negra VI Coxilha Negra VII Fazenda Rosário Planaltina Porto Seguro Rio Verde Faisa I, II, III, IV e V Icarai Santa Clara II, III, IV, V e VI Nossa Senhora da Conceição Licinio de Almeida Novo Horizonte
12 Alternative Energy Sources Biomass UTE Unid. Bio. Morro Vermelho UTE São João da Boa Vista UTE Boa Vista UTE Ben Bioenergia UTE Unid. Bio. Água Emendada UTE Quirinópolis (1ª etapa) UTE Quirinópolis (BC) UTE Baia Formosa UTE Porto das Águas UTE Angélica UTE Rio Brilhante F. I e II UTE Jataí UTE Cachoeira Dourada UTE Codora UTE Paraúna UTE Caçu I UTE Unid. Bio. Alto Taquari UTE Chapadão Agroenergia UTE Ferrari UTE Santa Isabel BC UTE Santa Luzia I UTE Lagoa da Prata F. I e II UTE CBB UTE Costa Pinto BC UTE Vale do Tijuco UTE Vale do São Simão UTE São José BC UTE Unid. Bio. Costa Rica UTE São Fernando UTE Bonfim UTE Iacanga UTE Ipaussu Bioenergia UTE Noble UTE Decasa UTE Pioneiros II BC UTE Santa Cruz AB F.I e II UTE Clealco- Queiroz UTE Colorado BC UTE Noroeste Paulista UTE Destilaria Andrade UTE Ester UTE Bevap UTE São João Biogás UTE UTE Interlagos Cocal II UTE Biopav II UTE Flórida Paulista BC UTE Barra Bioenergia UTE Rafard BC UTE Quatá BC UTE Conquista do Pontal UTE São Luiz PAC 2 PAC 1 PAC 1 com conclusão original após 2010
13 OIL AND GAS Exploration, Production and Natural Gas Transport Infrastructure
14 PRODUCTION AND EXPLORATION Increase oil and gas production Seismic assessment, drilling, plataform production To explore the reserves and enlarge national production, including the new Pre-Salt discoveries Value chain: naval industry, mecanic engineering, steel, chemical, precision engineering among other US$ 418,5 billion US$ billion after 2014 US$ 308 billion
15 PRODUCTION AND EXPLORATION Pre-Salt Reserves around 10.6 a 16 billion barrels of oil equivalent (boe) Total Pre-salt área: 149 mil km² Jubarte Parque das Baleias Sep/2008 first pre-salt production SÃO PAULO Carioca, Abaré e Iguaçu RIO DE JANEIRO Parati Iara C-M-101 Corcovado Bem-Te-Vi Caramba Azulão Guará Tupi, Iracema Júpiter
16 REFINEMENT, PETROCHEMESTRY and FERTILIZER Refinaria Premium I Refinaria Clara Camarão Refinaria Premium II Refinaria Abreu e Lima Petroquímica Suape PTA Petroquímica Suape PET POY FAFEN-SE Sulfato de amônio Fabrica de Amônia Fábrica de Fertilizantes Nitrogenados III Complexo Químico UFN-4 Complexo Petroquímico do Rio PAC 2 PAC 1 PAC 1 com conclusão original após 2010 US$ 76.6 billion US$ 41,8 billion Pós 2014 US$ 34,71 billion
17 HIGHWAYS
18 PAC HIGHWAYS Preliminary investment forecast Total - US$ 29 billion Type of investment Km Construction Maintenance Projects
19 FEDERAL HIGHWAY CONCESSION PROGRAM Central-South Region 54% of Brazil s GDP Length: 2,212.4 km BR-040/Distrito Federal-Goiás-Minas Gerais 937 km BR-116/Minas Gerais 817 km BR-101/Espírito Santo km Total Investment: US$5.5 billion GO BR-040 DF BR-116 BR-101 Concession bidding 1nd Half, 2011 MG Governador Valadares Belo Horizonte ES Vitória
20 CONCESSION MODEL Internal Rate of Return: 8.0% per year Reference value used on the 3 rd Phase of the Federal Highway Concession Program Term of Concession: 25 years Annual tariff adjustment according to inflation variation Investments described in the Highway Usage Program Constructions required (recovery, duplication, lighting, and others) Constructions conditioned to the volume of traffic (to expand capacity) Performance Parameters: paving, safety, signage, lighting, user assistance, and others. Focus on service quality Concessionaire performs the necessary investments in the most efficient way to meet the Performance Parameters *Allows the participation of Brazilian or foreign companies, financial institutions, pensions funds and private equity funds, separately or in consortiums
21 BR-040/DISTRITO FEDERAL-GOIÁS- MINAS GERAIS Connects the federal capital, Brasília, to two important cities: Belo Horizonte and Rio de Janeiro Length: 937 km Toll Plazas: 12 Basic Tariff US$ per 100 Km: 2.1 Toll*: US$ 1.4 Total Investment: US$1.8 billion GO BR-040 MG DF Belo Horizonte Concession bidding 1nd Half, 2011 *Prices on January, 2007
22 BR-116/MINAS GERAIS Important South-Southeast connection with the Northeast Length: 817 km Toll Plazas: 8 Basic Tariff US$ per 100 Km: 3.1 Toll*: US$ 3.5 Total Investment: US$2.3 billion MG BR-116 Governador Valadares Concession bidding 1nd Half, 2011 *Prices on January, 2007
23 BR-101/ESPÍRITO SANTO Connecting corridor linking RJ, SP and BA states, tourism hubs with high traffic volume. Crucial to cargo transportation Length: km Toll Plazas: 7 Basic Tariff US$ per 100 Km: 3.7 Total Investment: US$1.4 billion Concession bidding 1nd Half, 2011 BR-101 ES Vitória
24 RAILROADS
25 PAC RAILROADS Preliminary investment forecast Total - US$ 26 billion Type of investment Km Construction Studies High Speed Train 1.991
26 RAILROAD CONCESSION PROGRAM Participation in bidding processes North-South Railroad East-West Integration Railroad High-Speed Rail
27 NEW CONCESSION AND USAGE MODEL FOR NEW RAILROADS In study by the Government Separation of Infrastructure and Operations: VALEC is a public company which is the concessionaire for the North-South, East-West Integration and Midwest Integration Railroads Infrastructure management would continue to be under VALEC s responsibility, and totally separated from the operation The operation concessionaire (logistics operator) would acquire the right-of-way to use a preset number of tracks Goal is to optimize the usage of the railroad and reduce costs due to the efficiency gains
28 Port of Vila do Conde /PA Port of Itaqui/MA São Francisco Waterway Palmas/TO Figueirópolis/TO Anápolis/ GO Ilhéus/BA Estrela D Oeste/SP Port of Santos/SP Port of Itaguaí/RJ
29 NORTH-SOUTH RAILROAD SOUTH SECTION Port of Itaqui / MA 33% of Brazilian agricultural production 72% of agricultural land Large mineral reserves Outflow of the agro-industrial and mineral production to four ports Peru Açailândia Aguiarnópolis Araguaína Palmas Alvorad a Uruaç u Anápolis Santa Fé do Sul Araguaína Palmas Açailândia Aguiarnópolis North Section Length: 1,525 km Uruaçu South Section Anápolis Bidding for the logistic operator 1st Half, 2011 Estrela D Oeste (SP) Section to be Concessed Concessed Section
30 EAST-WEST INTEGRATION RAILROAD Outflow of the agricultural and mineral production Waterway integration Port of Vila do Conde / PA Port of Itaqui / MA Length: 1,527 km Figueirópolis (TO) Ilhéus (BA) Bidding for the logistic operator 1st Half, 2011 Port of Santos / SP Port of Itaguaí / RJ
31 HIGH-SPEED RAILS PLANNED Resende 36 million inhabitants São José dos Campos Taubaté Metropolitan Region of Campinas Volta Redonda Metropolitan Region of São Paulo Metropolitan Region of Rio de Janeiro Market Potential Metropolitan Region of São Paulo: 19 million inhabitants Metropolitan Region of Rio de Janeiro: 12 million inhabitants Metropolitan Region of Campinas: 2.5 million inhabitants Campinas - São Paulo - Rio de Janeiro 511 km Concession bidding 1st Half, 2011 Economic Importance Rio de Janeiro and São Paulo States concentrate 45 % of Brazil s GDP São Paulo is Latin America's biggest financial center, concentrating 70% of the stock market Rio de Janeiro is the biggest Brazilian tourism hub
32 HIGH-SPEED RAIL HSR Project scope Estimated investment: US$19.7 billion Deadline for operation start: 2016 Concessionaire responsible for the design, construction, operation and maintenance, complying with technical performance parameters; Auction to be open to all existing technologies Compulsory technology transfer Public sector participation: own capital and financing Documentation available at Technical studies on demand, alignment, geology, operation and economic-financial modeling completed and available
33 WORLD CUP 2014 HOST CITIES Manaus Fortaleza Natal Recife Cuiabá Salvador Brasília Curitiba São Paulo Belo Horizonte Rio de Janeiro Porto Alegre
34 RESPONSIBILITY ASSIGNMENT MATRIX Issue Ports Passenger Terminals Airports Passenger Terminals and Lanes Stadiums Construction, reform and maintenance Urban Mobility Hotels Responsible Federal Government Federal Government States and Municipalities States and Municipalities Private sector Federal Government financing
35 AIRPORTS
36 AIRPORTS Guidelines To provide airports a structure suitable for: Ensuring quality care and users comfort Meet the projected increased demand Improving the conditions for operational safety: Lane, yard, control tower Technological upgrade of the operating systems Total: 25 airports
37 AIRPORTS Historical Demand 1997 : 0.3 passengers carried per capita (163.8 million) 2008 : 0.6 passengers carried per capita (189.6 million) 6 milions of new passengers in 2009 After 2003: growth of 10% on passengers carried per capita Number of passengers: Million boardings + landings + connections % py % py % 80% International Domestic Fonte: EMBRATUR
38 WORLD CUP HOST CITIES AIRPORTS US$ Million, Preliminary Airport Belo Horizonte Brasília Cuiabá Curitiba Fortaleza Manaus Natal Porto Alegre Recife Rio de Janeiro Salvador São Paulo Total Investment 240,4 440,2 51,5 42,8 164,4 192,6 334,6 203,4 11,6 404,3 26,5 1153, ,2 Considering Guarulhos (US$720 million) and Viracopos (US$ 410 million)
39 AIRPORTS
40 PORTS
41 PORTS - World Cup Complementary investments to PAC Focus on passengers terminals Host cities with projected deficit in number of beds
42 PORTS CONSTRUCTION AND MODERNIZATION US$ 2.9 billion Build and modernize docks, piers, terminals, improve aquatic and land access Debureaucratization of port operations Passengers Terminals for the World Cup 2014 Reduced logistics costs Better operational efficiency Increased competitiveness Encourage private investments 48 PROJECTS 21 PORTS - US$ 2.9 billion Ventures Quantity Dredging 12 Port Infrastructure 24 Logistics Intelligence Systems 5 Passengers Terminals World Cup
43 URBAN MOBILITY
44 URBAN MOBILITY PAC 2 - Subway, LRT, BRT and bus lanes 1 st Phase US$ 6.8 billion launched Feb 16 th World Cup - projects selected in December 2009 Federal Government Financing Execution by state and city governments 2 nd Phase US$ 10.2 billion Public transportation systems in major urban centers US$ billion Investment Union Budget 3.4 Financing 6.8 TOTAL 10.2
45 URBAN MOBILITY WORLD CUP Summary per Modal US$ Million Modal Qty Project Value Financing Subway Bus Terminals Monitoring VLT Bus Corridors 18 1,138 1,067 Monorail 2 2, BRT 20 2,735 2,098 Total 50 6,817 4,587
46 URBAN MOBILITY FINANCING WORLD CUP Deadline: 4 years of grace period after signing the contract 20 years to repay after the grace period (30 years for public rail transport) Scope: Light Rail Trains (LRTs), Monorail and Bus Rapid Transit (BRT)
47 STADIUMS
48 STADIUM FINANCING Main financing characteristics: Amount: Up to 75% of the project value, limited to R$400 million Term: 3 years of grace period after signing the contract 12 years to repay after the grace period
49 STADIUMS SITTUATION Intervention Investment (R$ million) Capacity (thousand) Cost per seat (R$ thousand) Privatelyowned Curitiba Porto Alegre São Paulo Reform Reform Reform R$ 0.87 billion B. Horizonte Reform Brasília Reform Government- Owned Manaus Cuiabá Reconstruction Reconstruction R$ 3.09 billion R. Janeiro Reform Natal Construction Fortaleza Reform Public-private partnership Salvador Recife Reconstruction Construction R$ 1.74 billion Total 5, (*) Considering the basic design values. Including the constructions around the stadiums at São Paulo and Curitiba.
50 HOUSING AND SANITATION
51 MINHA CASA, MINHA VIDA PROGRAM 1st phase US$30.7 billion Production of 1 million homes to families with income up to US$2,784 equivalent to 14% of the housing deficit Subsidies for low-income families (up to US$1,670 per month) Long-term government partnership with private investors Establishment of a Guarantee Fund to reduce risks and costs 2nd phase US$40.3 billion Production of 2 million homes
52 SANITATION PAC 2 Water treatment Sewage and waste treatment Projects and studies To expand sewage collection and treatment system Improve waste treatment and reduce environmental damage TOTAL PROJECTED INVESTMENT- US$ 12.6 billion
53 Brazil Infrastructure Investment Opportunities Tokyo, Guilherme Walder Mora Ramalho Infrastructure Advisor Executive Office of the President of Brazil
Public Transport in Numbers
Nino Aquino ninoaquino@sinergiaestudos.com.br Sinergia Estudos e Projetos Ltda www.sinergiaestudos.com.br September 2009 Demand in bus systems Urban Bus Systems Main State Capitals* Passengers per month
Leia maisLogistics Investment Program. Ports
Logistics Investment Program Ports Purposes Promote the competitiveness and development of Brazilian economy End of entry walls Expansion of private investment Modernization of infrastructure and port
Leia maisLogistics Investment Program. Ports
Logistics Investment Program Ports Purposes Promote the competitiveness and development of Brazilian economy End of entry walls Expansion of private investment Modernization of infrastructure and port
Leia maisOpportunities for U.S. Companies in the Brazilian Intelligent Transportation Systems Market
Opportunities for U.S. Companies in the Brazilian Intelligent Transportation Systems Market Miguel Hernández Commercial Officer U.S. Consulate São Paulo, Brazil April 6, 2011 OUTLINE Overview U.S. Brazil
Leia maisGERAÇÃO E TRANSMISSÃO DE ENERGIA ELÉTRICA
PREVISÃO PRELIMINAR DE INVESTIMENTO R$ bilhões EIXOS 2011-2014 PÓS 2014 TOTAL GERAÇÃO DE ENERGIA ELÉTRICA 113,7 22,9 136,6 TRANSMISSÃO DE ENERGIA ELÉTRICA 26,6 10,8 37,4 PETRÓLEO E GÁS NATURAL 281,9 593,2
Leia maisCENTRAL COMISSION FOR THE NAVIGATION OF THE RHINE
CENTRAL COMISSION FOR THE NAVIGATION OF THE RHINE INLAND WATERWAY TRANSPORT IN TIMES OF GLOBALISATION PREPARATORY WORKSHOP AND SIDE EVENT PARAGUAY PARANÁ INLAND WATERWAY MARSEILLE (France), 13 MARCH 2012
Leia maisInfrastructure: Investments, Reforms and the new Concessions Program
Infrastructure: Investments, Reforms and the new Concessions Program Brasília, June 16th, 2015 Wagner Cardoso Executive Secretary of Infrastructure National Confederation of Industry 2 3 Summary PIL =
Leia maisWorkshop 2 Changes in Automotive Industry: New Markets Different Technologies?
Organization: Cooperation: Workshop 2 Changes in Automotive Industry: New Markets Different Technologies? Volkswagen do Brasil Cologne, August 25 th, 2008 Volkswagen do Brasil Present in Brazil since 1953
Leia maisURBAN AGE SOUTH AMERICA CONFERENCE DECEMBER 2008
URBAN AGE SOUTH AMERICA CONFERENCE DECEMBER 2008 José Luis Portella Secretary of Transport, State São Paulo The São Paulo 2025 Transport Strategy All rights are reserved by the presenter www.urban-age.net
Leia maisTransport in Brazil Overview. Dr. Giselle Xavier Brookes Visiting Research Fellow UDESC - State University of Santa Catarina - Brasil
Transport in Brazil Overview Dr. Giselle Xavier Brookes Visiting Research Fellow UDESC - State University of Santa Catarina - Brasil Brazil in the World http://www.geographicguide.com/maps.htm Latin America
Leia maisREAL ESTATE MARKET IN BRAZIL
REAL ESTATE MARKET IN BRAZIL JOÃO CRESTANA President of Secovi SP and CBIC National Commission of Construction Industry SIZE OF BRAZIL Population distribution by gender, according to age group BRAZIL 2010
Leia maisPrograma de Aceleração do Crescimento PAC Programa Minha Casa, Minha Vida Pré-Sal Copa 2014 Jogos Olímpicos e Paraolímpicos 2016
Brasil Oportunidades de Investimento Miriam Belchior Ministra de Estado Ministério do Planejamento, Orçamento e Gestão BRASIL VIVE UM MOMENTO EXITOSO Quatro movimentos estruturais explicam esse momento:
Leia maisBrazilian Port Sector
FEDERAL REPUBLIC OF BRAZIL Brazilian Port Sector New Model for Port Development Japan November, 2009 Pedro Brito Minister of Ports - Brazil Economic Environment Economic Environment Brazil has the ninth
Leia maisBrasil. 1º Congresso de Engenheiros da Língua Portuguesa
Brasil 1º Congresso de Engenheiros da Língua Portuguesa Maurício Muniz Secretário do Programa de Aceleração do Crescimento SEPAC Ministério do Planejamento, Orçamento e Gestão PAC PROGRAMA DE ACELERAÇÃO
Leia maisThe Current Situation of Water Supply and Business Opportunties in Pernambuco, Brazil
The Current Situation of Water Supply and Business Opportunties in Pernambuco, Brazil Flávio Coutinho Cavalcante Engineering Project Manager COMPESA flaviocoutinho@compesa.com.br Brazil Location BRAZIL
Leia maisFacts about PORTO ALEGRE City - BRAZIL
The City Facts about PORTO ALEGRE City - BRAZIL DADOS SOBRE PORTO ALEGRE 1.420.000 inhabitants (IBGE forecast for 2008). 1.600.000 inhabitants (IBGE forecast for 2014). Urban area = 496,8 km2 =..sq miles.
Leia maisBRAZILIAN RESEARCH, DEVELOPMENT AND DEMONSTRATION ACTIVITIES
Ministry of Mines and Energy BRAZILIAN RESEARCH, DEVELOPMENT AND DEMONSTRATION ACTIVITIES 5 th STEERING COMMITTEE MEETING João de Nora Souto Deputy Minister for Oil, Natural Gas and Renewable Fuels SPGMME
Leia maisPotência Nominal UF Tipo da Usina Nome da Usina (MW) CE CGE Bons ventos 50 CE CGE Formosa 104,4 CE CGE Volta do Rio 42 CE CGE Praia do Morgado 28,8
Geração existente e com previsão de entrada em operação até dezembro de 2015, com ato de autorização anterior à publicação do Edital do LER 2013, considerada nos estudos da Margem de Transmissão. Potência
Leia maisECONOMIC DEVELOPMENT, ENERGY, INDUSTRY AND SERVICES STATE SECRETARIAT RIO DE JANEIRO STATE: ECONOMIC OVERVIEW
ECONOMIC DEVELOPMENT, ENERGY, INDUSTRY AND SERVICES STATE SECRETARIAT RIO DE JANEIRO STATE: ECONOMIC OVERVIEW Rio de Janeiro that you already know or have heard about... ...and the Rio de Janeiro that
Leia maisAcquisition of Faculdade Nossa Cidade FNC
Acquisition of Faculdade Nossa Cidade FNC Rio de Janeiro, July 7, 2015 Student Distributiion Area of Influence Carapicuíba Market Location Status Area of influence Area of Influence Distances: Between
Leia maisPedro Spadale. Head of International Relations Executive Office of the Governor Government of the State of Rio de Janeiro
Pedro Spadale Head of International Relations Executive Office of the Governor Government of the State of Rio de Janeiro Location Southeast of Brazil (57% of national GDP) Area 43,697 km 2 (0.5% of
Leia maisBRAZILIAN HIGH SPEED LINE (RIO DE JANEIRO SÃO PAULO CAMPINAS) APTA RAIL 2011
BRAZILIAN HIGH SPEED LINE (RIO DE JANEIRO SÃO PAULO CAMPINAS) APTA RAIL 2011 HÉLIO MAURO FRANÇA Executive Superintendent - ANTT Boston (MA), June 13 2011 RIO SÃO PAULO HIGH SPEED LINE - Background In recent
Leia maisColor variant: Siemens White
2º Forum da Responsabilidade Social das Organizações A Glocal Company Color variant: Siemens White Key Figures - Siemens Global Dados Gerais Americas 25% 22% 33% 101 19.1 96 Europe (excl. Germany) 27%
Leia maisBrazilian Coal Industry Overview and Perspectives
INTERNATIONAL WORKSHOP ON COAL TECHNOLOGY PETROBRAS/ABCM Brazilian Coal Industry Overview and Perspectives Eng. Fernando Luiz Zancan Brazilian Coal Association ABCM Rio de Janeiro, 14 March 2007 Brazilian
Leia maisThe Best Business Opportunity with High Return on Investment
Port Itaqui Area The Best Business Opportunity with High Return on Investment Willer Pos whpos@whpos.com.br Port Itaqui Fonte: Google Earth Port Itaqui- Present Layout Iron ore stock pile area VALE MPX
Leia maisAdinoél Sebastião /// Inglês Tradução Livre 20/2013
TEXTO WWW.ADINOEL.COM Spending for the 2014 World Cup in Brazil explodes beyond prediction and reaches R$ 26.5 billion The cost for organizing the 2014 World Cup has now reached R$26.5 billion. The figure
Leia maisBrazil: Wind Energy Opportunities
Brazil: Wind Energy Opportunities Anne McIvor, Cleantech Investor BWEC 2012 2-3 April - São Paulo Brazilian Wind Energy The Brazilian Wind States BAHIA BAHIA: Projects Focus on semi-arido (semi-desert)
Leia maisSeleção Territorial Enfrentamento a Violência contra Juventude Negra Classificação 2010
Posição Nome do Município Estado Região RM, RIDE ou Aglomeração Urbana 1 Salvador BA Nordeste RM Salvador 2 Maceió AL Nordeste RM Maceió 3 Rio de Janeiro RJ Sudeste RM Rio de Janeiro 4 Manaus AM Norte
Leia maisBrazilian Ports: Institutional overview and Investment opportunities
Brazilian Ports: Institutional overview and Investment opportunities Presentation for the World Economic Forum on Latin America Panama City April 2014 MINISTRY OF PORTS SECRETARIA DE PORTOS DA PRESIDÊNCIA
Leia maisPeter Øye, CEO & President, Markleen AS. Response and Containment systems
Peter Øye, CEO & President, Markleen AS Response and Containment systems What we do: Markleen supplies complete Oil Spill Response Systems for PSVs to NOFO and Petrobras standards. Oil Booms Skimmer Fast
Leia mais4Q06 and 2006 Conference Call Presentation
4Q06 and 2006 Conference Call Presentation February 15, 2007 Peru Bolivia Argentina Cuiabá Guianas Uruguai Itaipú V. Conde Colinas Miracema Gurupi Tucuruí Imperatriz Curitiba B.J. Lapa São Luís Teresina
Leia maisBrasil. Oportunidades de Investimento Batimat 2011. Miriam Belchior. Ministra de Estado Ministério do Planejamento, Orçamento e Gestão
Brasil Oportunidades de Investimento Batimat 2011 Miriam Belchior Ministra de Estado Ministério do Planejamento, Orçamento e Gestão BRASIL VIVE UM MOMENTO EXITOSO Quatro movimentos estruturais explicam
Leia maisSALA DE MONITORAMENTO DO ATENDIMENTO AO TURISTA TOURISM DATA MONITORING OFFICE
SALA DE MONITORAMENTO DO ATENDIMENTO AO TURISTA TOURISM DATA MONITORING OFFICE Quarta-Feira, 02 de julho de 2014 Wednesday, July 1 st, 2014 Max. 23 o C/ 73,4 o F Min. 9 o C/ 48,2 o F PRÓXIMOS JOGOS NEXT
Leia maisCompetitiveness in the Brazilian economy: challenges & opportunities
Competitiveness in the Brazilian economy: challenges & opportunities Erik Camarano MBC CEO Thursday, June 6th, 2013 Woodrow Wilson International Center for Scholars 6th Floor Auditorium SPONSORS SHORT-TERM
Leia maisCompartilhando Energia Humana. Sharing Human Energy
Compartilhando Energia Humana Sharing Human Energy A Chevron Brasil tem como estratégia e valor um plano de investimento social voltado para o incentivo à qualificação profissional e ao empreendedorismo
Leia maisE&P Infrastructure Espírito Santo State
E&P Infrastructure Espírito Santo State JULIO BUENO Secretário de Estado de Desenvolvimento Econômico e Turismo do Estado do Espírito Santo Rio de Janeiro-RJ, março 2004 Espírito Santo Geographical Location
Leia maisSAO PAULO, BRAZIL AND SOUTH AMERICA
SAO PAULO, BRAZIL AND SOUTH AMERICA Brazil Sao Paulo State Area (km²)¹ Population (thousand inhab)² % Population Brazil 8.514.877 183.987 - Sao Paulo 248.210 39.827 21,65% RMSP 7.944 19.221 10,44% ¹ IBGE
Leia maisGlobal Grain North America Chicago
Global Grain North America Chicago May/2014 Marcos Rubin Rally da Safra ( Crop Tour ) 11th Edition of the Project From jan to mar (summer crops) May (Corn 2 nd Crop) Soybeans and Corn Samples 2014 Edition
Leia maisSALA DE MONITORAMENTO DO ATENDIMENTO AO TURISTA TOURISM DATA MONITORING OFFICE. Max. 26 C/ 78,8 F 15 C/ 59 F JOGOS DE HOJE/ TODAY S MATCHES
SALA DE MONITORAMENTO Max. Min. 26 C/ 78,8 F 15 C/ 59 F DO ATENDIMENTO AO TURISTA TOURISM DATA MONITORING OFFICE JOGOS DE HOJE/ TODAY S MATCHES BRA ME CRO CAM 17:00 NATAL 13:00 Quartafeira, 12 de junho
Leia mais2014 World Cup FIFA Brazil
Copa do Mundo da FIFA 2014 Brasil 2014 World Cup FIFA Brazil JORNADAS TÉCNICAS BRASIL AS INFRAESTRUTURAS NAS CIDADES SEDE DA COPA DE FUTEBOL Evoluçãosócio-econômicado Brasil Entre as dez maiores economias
Leia maisIT 204 Análise Operacional e Gerencial de Aeroportos Prof. Carlos Müller sala 2134 (muller@ita.br) 1 º semestre / 2014 Versão 2 Programa:
Programa: Requisito recomendado: IT-203 Aeroportos. Requisito exigido: não há. Horas semanais: 3-0-6. Análise de terminais aeroportuários sob o ponto de vista operacional. Conceituação de capacidade do
Leia maisConferência Internacional
Conferência Internacional Lisboa Maio de 2008 A INFRAERO Brazil Airport Administration 8 Superintendências Regionais 8 Regional Superintendences 67Aeroportos, (32 Internacionais) 67 Airports, 32 Internationals
Leia maisMulticriteria Impact Assessment of the certified reference material for ethanol in water
Multicriteria Impact Assessment of the certified reference material for ethanol in water André Rauen Leonardo Ribeiro Rodnei Fagundes Dias Taiana Fortunato Araujo Taynah Lopes de Souza Inmetro / Brasil
Leia maisSALA DE MONITORAMENTO DO ATENDIMENTO AO TURISTA TOURISM DATA MONITORING OFFICE
SALA DE MONITORAMENTO DO ATENDIMENTO AO TURISTA TOURISM DATA MONITORING OFFICE Quinta-feira, 03 de julho de 2014 Thursday, July 3 rd, 2014 Max. 28 o C/ 82,4 o F Min. 16 o C/ 60,8 o F PRÓXIMOS JOGOS NEXT
Leia maisMaio. Office Of Energy Efficiency and Renewable Energy U.S. Energy Department (DOE) Washington, DC
Dia Nome do Evento Realizador Local Maio 03 ACORE U.S.-China Renewable Energy Industry Forum American Council On Renewable Energy (ACORE) Washington, DC 04 CEO Leadership Series Luncheon Featuring U.S.
Leia maisLote Produzidos Cidade UF Qte faturada
Lote Produzidos Cidade UF Qte faturada 1400008703 BELEM PA 339 1400008703 BELO HORIZONTE MG 2.034 1400008703 BRASILIA DF 1.356 1400008703 CONGONHAS MG 54 1400008703 CUIABA MT 678 1400008703 GOIANIA GO
Leia maisCAIXA ECONÔMICA FEDERAL CONCURSO PÚBLICO PARA FORMAÇÃO DE CADASTRO DE RESERVA PARA O CARGO DE TÉCNICO BANCÁRIO NOVO CARREIRA ADMINISTRATIVA
Técnico Bancário Novo AC Cruzeiro do Sul 1618 CR* Técnico Bancário Novo AC Rio Branco 6648 CR * Técnico Bancário Novo AC Sena Madureira 1065 CR* Técnico Bancário Novo AL Maceió 22524 CR * Técnico Bancário
Leia maisClimate Change - Coal Overview
CSLF : Capacity Building Climate Change - Coal Overview Fernando Luiz Zancan President - Associação Brasileira do Carvão Mineral - ABCM Salvador - 08 September 2008 BRAZILIAN COAL INDUSTRY Resources: 31,7
Leia maisSALA DE MONITORAMENTO DO ATENDIMENTO AO TURISTA TOURISM DATA MONITORING OFFICE
SALA DE MONITORAMENTO DO ATENDIMENTO AO TURISTA TOURISM DATA MONITORING OFFICE SextaFeira, 13 de junho de 2014 Friday, June 13 th, 2014 Max. 26 o C/ 78,8 o C Min. 15 o C/ 59 o F JOGOS DE HOJE/ TODAY S
Leia maisCRONOGRAMA DE APRESENTAÇÃO DOS TRABALHOS CR3+2015 11.11.15
Horários 13h30 às 15h30 11.11.15 13h30 às 15h30 SESSÃO 1: APRESENTAÇÃO DE TRABALHOS Sala 1 Painel Estratégias e Horários Sala 2 - Painel Políticas Públicas e Práticas Sustentáveis P1 Consumo e Produção
Leia maisGRUPO VII PLANEJAMENTO DE SISTEMAS ELETRICOS (GLP) POR UM BRASIL SOLAR.
GRUPO VII PLANEJAMENTO DE SISTEMAS ELETRICOS (GLP) POR UM BRASIL SOLAR. Benedito José Pontes Parente Pedro Bezerra de Carvalho Neto 1 / 2 All the Routes Lead us to the Sun King... MME Energy Expansion
Leia maisSECTOR OF ACTIVIITY FOOD ENERGY COTTON BIODIESEL SOYA VEGETAL OIL CORN ETHANOL
Results 08/15/2011 SECTOR OF ACTIVIITY FOOD ENERGY COTTON SOYA CORN BIODIESEL VEGETAL OIL ETHANOL BRAZILIAN BIODIESEL MARKET 2005 2007 Blend: up to 2% 1st Sem/08 Blend: min. 2% Jul/08 Jun/09 Blend: min.
Leia maisSalud Brasil SECRETARIA DE VIGILÂNCIA EM SAÚDE
Salud Brasil SECRETARIA DE VIGILÂNCIA EM SAÚDE IV EXPOEPI International Perspectives on Air Quality: Risk Management Principles for Oficina de Trabalho: Os Desafios e Perspectivas da Vigilância Ambiental
Leia mais4Q14 and 2014 PRELIMINARY OPERATIONAL RESULTS Total Pre-Sales reached R$1.4 billion in 2014
4Q14 and 2014 PRELIMINARY OPERATIONAL RESULTS Total Pre-Sales reached R$1.4 billion in 2014 Mogi das Cruzes, January 19, 2015 Helbor Empreendimentos S.A. (BM&FBOVESPA: HBOR3), a residential and commercial
Leia maisSão Paulo State in the Brazilian Context
São Paulo State in the Brazilian Context Brazil and São Paulo Comparison São Paulo s Share Territory 8.515.000 248.000 Km² Km² 3% Population 193.9 41.9 million million 22% GDP nominal US$ 2.475 billion
Leia maisENERGIA ENERGY USINA HIDRELÉTRICA DE ILHA DOS POMBOS - LIGHT - ENGINEERING DA EPC FORMADA PARA REABILITAÇÃO E REPOTENCIAÇÃO DA USINA
ENERGIA ENERGY USINA HIDRELÉTRICA DE ILHA DOS POMBOS - LIGHT - ENGINEERING DA EPC FORMADA PARA REABILITAÇÃO E REPOTENCIAÇÃO DA USINA ILHA DOS POMBOS HYDROELECTRIC POWER PLANT - LIGHT - ENGINEERING SERVICES
Leia maisAngola : business opportunities highlight
13-01-2014 O Ministério da Energia e Águas da República de Angola, no âmbito do Plano de Desenvolvimento do Subsector Eléctrico de Angola alicerçado na Política e a Estratégia de Segurança Energética Nacional
Leia maisSchmidt, Valois, Miranda, Ferreira & Agel - Advogados
Schmidt, Valois, Miranda, Ferreira & Agel - Advogados Deuxièmes rencontres Franco - Brésiliennes de la Société de Législation Comparée Contractual Renegotiation with Public Entities June - 2010 Index Principles
Leia maisCity of Curitiba Institute for Research and Urban Planning of Curitiba
City of Curitiba Institute for Research and Urban Planning of Curitiba Cléver Ubiratan Teixeira de Almeida President Energy Efficiency in Cities: Curitiba s Green Line World Bank s Energy Week April 2009
Leia maisIts structure focuses on servicing the Oil and Gas market, including:
Gavea Logistics is a logistics operator that offers solutions in Port, Maritime and Land logistics at its terminals located in Rio de, and. Its structure focuses on servicing the Oil and Gas market, including:
Leia maisMOBILITY AND SUSTAINABILITY Rosario, May 9th 14th, 2011. jaime lerner arquitetos associados
MOBILITY AND SUSTAINABILITY Rosario, May 9th 14th, 2011 STRATEGIC VISION AND URBAN STRUCTURE VITA, THE TURTLE OTTO, THE AUTOMOBILE ACCORDION, THE FRIENDLY BUS DRAWING THE CITIES... URBAN STRUCTURE OF
Leia maisBalance of supply and demand Cemig Geração e Transmissão
Balance of supply and demand Cemig Geração e Transmissão Bernardo Afonso Salomão de Alvarenga Chief Trading Officer May 28 1/XX Disclaimer Some statements contained in this presentation are forward-looking
Leia maisand the Municipality of SERTÃ
RETS Launch Conference 3rd February 2010 Casa da Cultura da Sertã SERTÃ, Portugal Renewable Energies and the Municipality of SERTÃ, Mayor The participation of Sertã in RETS is the continuation of its journey
Leia maisEnergy Balance. Rio de Janeiro, 27th October 2011 Olga C. R. L. Simbalista. Corporate Participation
XXVIII National Seminar on Large Dams Energy Balance Rio de Janeiro, 27th October 2011 Olga C. R. L. Simbalista Director of Planning,, Business Manegement and Corporate Participation BRAZIL AND WORLD DATA
Leia maisSALA DE MONITORAMENTO DO ATENDIMENTO AO TURISTA TOURISM DATA MONITORING OFFICE
SALA DE MONITORAMENTO DO ATENDIMENTO AO TURISTA TOURISM DATA MONITORING OFFICE TOURISM DATA MONITORING OFFICE Max. 21 o C/ 69,8 o F Min. 12 o C/ 53,6 o F ARG 2 ALE 1 HOL 3 Segunda-feira, 14 de julho de
Leia maisFuture Trends: Global Perspective. Christian Kjaer Chief Executive Officer European Wind Energy Association
Future Trends: Global Perspective Christian Kjaer Chief Executive Officer European Wind Energy Association Brazil Wind Power 2010 Rio de Janeiro 1 September 2010 Members include the following leading players:
Leia maisO Futuro da Gestão no Brasil e no Exterior
O Futuro da Gestão no Brasil e no Exterior 7º Congresso ANBIMA de Fundos de Investimento São Paulo, 14 de maio 2013 Daniel Celeghin, Sócio Resumo 1. Quem somos 2. Perspectiva ex-brasil : cinco fatores
Leia maisLow Carbon Scenarios for Brazil. Amaro Pereira PPE/COPPE/UFRJ
Low Carbon Scenarios for Brazil Amaro Pereira PPE/COPPE/UFRJ Project Team Co-ordinators Prof. Emilio La Rovere and Carolina Dubeux Technical team Amaro Pereira (Energy) Anamélia Medeiros (Agriculture)
Leia mais7º Programa Quadro Tema ENERGIA Os próximos concursos: tópicos e destaques
7º Programa Quadro Tema ENERGIA Os próximos concursos: tópicos e destaques Helder Gonçalves Delegado Nacional tema Energia TÓPICOS DO TEMA ENERGIA WP 2012 ACTIVITY ENERGY 1; Hydrogen and Fuel Cells ACTIVITY
Leia maisWWW.ADINOEL.COM Adinoél Sebastião /// Inglês Tradução Livre 74/2013
PASSO A PASSO DO DYNO Ao final desse passo a passo você terá o texto quase todo traduzido. Passo 1 Marque no texto as palavras abaixo. (decore essas palavras, pois elas aparecem com muita frequência nos
Leia maisRegistration Form - 2013 - ALL - AMÉRICA LATINA LOGISTICA S.A. Version : 3
Index: Company s Profile ALL AMÉRICA LATINA LOGÍSTICA S.A. Corporate Taxpayers ID (CNPJ/MF) 02.387.241/0001-60 Companies Registry (NIRE) 413 00 019886 Publicly-held Company REGISTRATION FORM General Information
Leia maisA Experiência Internacional e os Modelos Contratuais em Projetos de Infraestrutura Rio de Janeiro, 16-17 de abril de 2012
Pinheiro Neto Advogados ABCE FEPAC SINAENCO Parcerias para o Desenvolvimento - PPPs e Concessões A Experiência Internacional e os Modelos Contratuais em Projetos de Infraestrutura Rio de Janeiro, 16-17
Leia maisEnergy Management: 2009/2010
Energy Management: 2009/2010 Class# T05 Energy Prices, basics and dynamics Prof. Miguel Águas miguel.aguas@ist.utl.pt ELECTRICITY Class# T05: Energy Prices, basics and dynamics Slide 2 of 53 National electricity
Leia maisPanel 3: Improving the Delivery Services
UNITED NATIONS PUBLIC SERVICE DAY AND AWARDS CEREMONY Technical Seminar on Innovation in the Delivery of Public Services Panel 3: Improving the Delivery Services IMPLEMENTATION OF THE SELF-SUSTAINABLE
Leia maisRecuperação, Alargamento e Ampliação
Recuperação, Alargamento e Ampliação do Cais do Porto de Vitória ES Evolução do Monitoramento Evolução do Monitoramento Nos últimos dois anos o PAC 2 concluiu empreendimentos no valor de R$ 328,2 bilhões,
Leia maisActive Ageing: Problems and Policies in Portugal. Francisco Madelino Berlin, 17 October 2006
Active Ageing: Problems and Policies in Portugal Francisco Madelino Berlin, 17 October 2006 ACTIVE AGEING 1. Demographic Trends in Portugal 2. Financial Implications of the Active Ageing on Social Security
Leia maisSALA DE MONITORAMENTO DO ATENDIMENTO AO TURISTA TOURISM DATA MONITORING OFFICE
SALA DE MONITORAMENTO DO ATENDIMENTO AO TURISTA TOURISM DATA MONITORING OFFICE TOURISM DATA MONITORING OFFICE Sexta-feira, 11 de julho de 2014 Friday, July 11 th, 2014 Max. 17 o C/ 62,6 o F Min. 13 o C/
Leia maisMINISTÉRIO DA PREVIDÊNCIA E ASSISTÊNCIA SOCIAL SECRETARIA DE PREVIDÊNCIA COMPLEMENTAR. Sao Paulo May 23, 2002
6HFRQG2(&'&RQIHUHQFHRQ 3ULYDWH3HQVLRQVLQ%UD]LO 0LQLVWU\RI6RFLDO6HFXULW\DQG$VVLVWDQFH RI%UD]LO )DELR2KDUD,VKLJDPL 6HFUHWDULDWRI&RPSOHPHQWDU\3HQVLRQ 5RRP'RFXPHQW1ƒ6HVVLRQ Sao Paulo May 23, 2002 6HFRQG2(&'&RQIHUHQFHRQ
Leia mais"Oportunidades e desafios nos serviços de logística no setor de P&G. 22 de Agosto de 2013
"Oportunidades e desafios nos serviços de logística no setor de P&G 22 de Agosto de 2013 SUMÁRIO 1.INTRODUÇÃO 2.RELEVÂNCIA DO SETOR DE P&G NO BRASIL 3.CENÁRIO ATUAL 4.DESAFIOS 5.CONCLUSÃO SUMÁRIO 1.INTRODUÇÃO
Leia maisOctober, 2013. Um Olhar Estratégico para o Setor de Seguros de Automóvel no Brasil
October, 2013 Um Olhar Estratégico para o Setor de Seguros de Automóvel no Brasil AGENDA Visão da Industria de Seguros (Brasil x Mundo) Drivers que movem a Indústria Análise da Penetração da Indústria
Leia maisBrazil China Energy Dialogue
LETS -THE INFRASTRUCTURE WEEK Brazil China Energy Dialogue Mauricio Aredes COPPE/UFRJ discuss the Chinese presence in the Brazilian energy sector and what are the prospects of this strategic partnership
Leia maisWorkshop (6) Energy Efficiency
Member of the Executive Board, MAN Diesel Blumenau, November 19 th th 2007 The MAN Group today Business areas Internationally active manufacturer of vehicles, engines and machinery Approx. 13 billion in
Leia maisBanco Bradesco S.A. Calendar of Corporate Events - 2011
Calendar of Corporate s - 2011 Information on the Company Company Name Corporate Head Office Address Internet Address Investor Relations Officer Investor Relations Contact Newspapers in which corporate
Leia maisPeering Fórum - April 30, 2018 in Panamá - IX.br - 1
Peering Fórum - April 30, 2018 in Panamá - IX.br - 1 Panamá, PA 30 de Abril de 2018 IX.br(PTT.br) KIT PTT e Novas Localidades Galvão Rezende Julio Sirota Equipe
Leia maisPassenger cabotage transport in Brazil: it is "trade or navigation in Brazilian coastal waters.
Passenger cabotage transport in Brazil: it is "trade or navigation in Brazilian coastal waters. Center for Legal Studies Department of Law Laboratory studies in law and science waterway navigation 1/10
Leia maisBrazil s non-domestic energy and buildings context. Roberto Lamberts LabEEE-UFSC
Brazil s non-domestic energy and buildings context Roberto Lamberts LabEEE-UFSC www.labeee.ufsc.br Brazil x World Consumption per capita is different Emission are different End uses are different Space
Leia maisCollaborative Networks the rsptic example espap Entidade de Serviços Partilhados da Administração Pública, I.P. Direitos reservados.
Collaborative Networks the rsptic example 2017 espap Entidade de Serviços Partilhados da Administração Pública, I.P. Direitos reservados. 1 Collaborative Networks for an Intelligent State Intelligent State
Leia maisEnergy Storage Seminar
IEEUSP Energy Storage Seminar Characteristics of Brazilian electric system and potential contributions of energy storage Prof. Ildo Luís Sauer Realização Promoção Apoio Participação: U.S. CONSULATE, SÃO
Leia maisSALA DE MONITORAMENTO DO ATENDIMENTO AO TURISTA
SALA DE MONITORAMENTO DO ATENDIMENTO AO TURISTA Max. 16 o C/ 60,8 o F Min. 12 o C/ 53,6 o F 3 o e 4 o LUGARES 3 rd AND 4 th PLACES 12 DE JULHO/ JULY 12 th FINAL FINAL MATCH 13 DE JULHO/ JULY 13 th TOURISM
Leia maisBrazil begins a new development cycle
The role of the BNDES in the Brazilian Economy World Economic Forum Davos, January 29 th, 2011 Luciano Coutinho President Brazil begins a new development cycle The Brazilian economy may grow beyond 5%
Leia maisInstituto de Engenharia de Sistemas e Computadores: Investigação e Desenvolvimento em Lisboa
Instituto de Engenharia de Sistemas e Computadores: Investigação e Desenvolvimento em Lisboa Arlindo Oliveira 1 Brief history Research Institute established January 2000. Private Not-for Profit Institution
Leia maisBlack Sea Grain Conference. Kiev, Ukraine
Black Sea Grain Conference Kiev, Ukraine South American Soybeans and Corn Production and Trading Marcos Rubin April/14 About Agroconsult, visit our website www.agroconsult.com.br Perspectivas para os Mercados
Leia maisSM- ICG Industry Day HELIBRAS AIRBUS HELICOPTERS SMS : How to engage in all levels
SM- ICG Industry Day HELIBRAS AIRBUS HELICOPTERS SMS : How to engage in all levels Antonio Modesto Safety Manager Wagner Flores Safety Coordinator November 2014 AGENDA Org acronym / name of accountable/
Leia maisELEnA European Local ENergy Assistance
ECO.AP Programa de Eficiência Energética na Administração Pública ELEnA European Local ENergy Assistance Lisboa, 6/03/2015 Desafios 1 Conhecimento: a) Edifícios/equipamentos; b) Capacidade técnica; c)
Leia maisWWW-YES-2009-Brazil: Water survey summary
Survey area Area de enquetes WWW-YES Brazil 2009 Mexico France Portugal Italy Water Survey Questionário sobre «águas» Costa Rica Colombia Brazil Uruguay Cameroon Countries and cities Países e cidades 9
Leia maisA -- Como líder de projecto, dirigiu as equipes de preparaçao de 8 projectos de saúde em diferentes países da América Latina e da África:
ANEXO - Projectos A -- Como líder de projecto, dirigiu as equipes de preparaçao de 8 projectos de saúde em diferentes países da América Latina e da África: Brasil: NE Endemic Disease Control, supervisão
Leia maisEnergy Management :: 2007/2008
:: 2007/2008 Class # 8 Energy Efficiency in Buildings Prof. Paulo Ferrão ferrao@ist.utl.pt Carlos Soares, MSc c.soares@enerone.eu Energy systems Energy use in buildings Air conditioning; Ventilation; Artificial
Leia maisChallenges in Logistics in Latin America. Caio Fontana Universidade Federal de São Paulo
Challenges in Logistics in Latin America Caio Fontana Universidade Federal de São Paulo Scenario Road Network Difficulty for intermodality Fleet of passenger vehicles Logistics planning long distances
Leia maisVisão Geral do Programa de Portos
Visão Geral do Programa de Portos São Paulo, 3 de setembro de 2013 O que é a EBP? Aporte de capital em partes iguais Um voto cada no Conselho Desenvolvimento de projetos de infraestrutura: Em parceria
Leia maisREGIONAL AIRPORT AND URBAN HELIPORT CONCESSIONS
REGIONAL AIRPORT AND URBAN HELIPORT CONCESSIONS The Future of Brazil Dorieldo Luiz dos Prazeres Civil Aviation Regulation Specialist SUMMARY Airports Commercial Exploitation Overview; Regional Airports
Leia mais